Chemaf’s flagship Mutoshi and Etoile copper-cobalt projects in the Democratic Republic of Congo (DRC) are moving towards full operations under new ownership, the company said, with commissioning at Mutoshi planned for February 2027 and construction at Etoile due to finish by the end of December 2026.
Chemaf said the two sites have already preserved 2,000 existing jobs and created 3,000 new ones, and that teams on both sites are working to keep commissioning on schedule.
Commissioning at Mutoshi, near Kolwezi, is scheduled to begin in February 2027. At full capacity, the plant is designed to produce 50,000 tonnes of copper and 16,000 tonnes of cobalt a year. The company has not given a date for reaching that capacity.
Construction at Etoile is due to be completed by the end of December 2026. At full capacity, the site will be capable of producing 24,000 tonnes of copper and 4,000 tonnes of cobalt a year. Together, the two projects would add up to 74,000 tonnes of copper and 20,000 tonnes of cobalt a year, based on the company’s figures.
In March 2026, Virtus Lloyds Minerals Holding (VLMH) completed its acquisition of Chemaf, the developer of Mutoshi. VLMH is a joint venture between US-based Virtus Minerals and India’s Lloyds Metals and Energy. Lloyds is the operating partner, and the new owners plan to complete the Mutoshi plant.
Chemaf described the change of ownership as a new chapter that reflects a growing strategic partnership between the DRC and the United States. It said the investment from Virtus and Lloyds is aimed at creating opportunities for Congolese people.
Under the new management, Chemaf said it is investing in Congolese talent, introducing new technologies and transferring skills so local employees can lead the industry in future.
The company also said it is working with communities around its operations to expand access to healthcare, support local farmers, create opportunities for children and improve access to clean water. It said it wants children growing up near its sites to become the engineers, doctors and teachers who shape the DRC’s future.
Engineering firm METC said it has been involved with Mutoshi since 2017, when it delivered the plant’s detailed engineering, from process flow diagrams and piping and instrumentation diagrams through to layout and civil, mechanical and electrical design. It is now providing engineering support and procurement services to Chemaf’s construction team as the plant is completed. METC said the plant had stalled for several years and that it was a pleasure to be back on the project and to see it on its way to production. It thanked Chemaf and wished Virtus, Lloyds and the Chemaf team success with the restart.